- Fluence Energy signed a record US$3.5 billion of battery storage orders in its fiscal fourth quarter, more than it booked in all of fiscal 2025.
- The backlog reached US$8.9 billion at 30 September 2026, up 68% year on year, equal to nearly four years of current revenue.
- Revenue and margins fell in the same quarter: fourth-quarter revenue dropped 29% and gross margin turned negative as factory delays hit deliveries.
The split inside the numbers is the story. Fluence’s customers kept signing through a September guidance cut, with about 70% of the quarter’s orders landing after the warning, including a US$586 million order from a single hyperscaler. The orders are not the constraint. The constraint is a contract manufacturer’s facility in Houston, where a slow ramp-up left shipments behind schedule, pushed inventory to US$968.6 million, and forced the company to pay liquidated damages for late projects.
Fluence is one of the world’s largest battery storage integrators, selling its Gridstack and Smartstack systems plus services and software to utilities, developers and, increasingly, data centre operators. Its fiscal year ends on 30 September, so the quarter reported on 23 November covers July to September 2026, with the earnings call held on 24 November.
Fluence record orders top US$3.5 billion in one quarter
Order intake of more than US$6.2 billion for fiscal year 2026 included US$3.5 billion signed during the fourth quarter, more than double the levels of the fourth quarter and fiscal year 2025 respectively, and the largest amounts in the company’s history. The fourth-quarter figure alone exceeds the total orders Fluence booked in all of fiscal 2025. Axel Meier, interim chief executive officer, said: “Demand for our product is the strongest in Company history based on our record fourth quarter orders of US$3.5 billion which exceeds the total for all of fiscal year 2025. With a backlog of US$8.9 billion in hand as of the end of this fiscal year, we are well-positioned to execute on growing our revenue over the next few years.”
The gigawatt figures behind the dollars show the same surge. Energy storage product orders reached 4.8 GW in the quarter, up 220% on the 1.5 GW contracted in the same quarter of 2025, and 9.0 GW for the full year against 3.4 GW in fiscal 2025. Contracted product backlog stood at 16.8 GW, up 84.6% from 9.1 GW a year earlier, and the product pipeline reached 44.5 GW. Deployed storage rose to 8.1 GW and 20.8 GWh, from 6.8 GW and 17.8 GWh.
About 70% of the fourth-quarter orders were booked after Fluence cut its fiscal 2026 guidance in mid-September, which management presented on the earnings call as evidence that customers kept buying through the warning. The quarter also included US$586 million of orders from a single hyperscaler customer. US orders now make up 70% of the backlog, up from 58% a year earlier, and data centres account for 10% of the backlog, the fastest-growing customer segment.
| Fluence fiscal year | FY2026 | FY2025 | Change |
|---|---|---|---|
| Order intake | US$6.2 billion+ | Not disclosed as a total | Q4 intake US$3.5 billion, a record |
| Backlog (30 September) | US$8.9 billion | US$5.3 billion | +68% |
| Total revenue | US$2.3 billion | US$2.3 billion | +3% |
| GAAP gross margin | 2.8% | 13.1% | Down 10.3 points |
| Net loss | US$273.9 million | US$68.0 million | Loss widened 4x |
| Adjusted EBITDA | Negative US$202.8 million | US$19.5 million | Swung negative |
| Contracted product backlog | 16.8 GW | 9.1 GW | +84.6% |
Revenue falls as Houston factory delays bite
Revenue of US$2.3 billion for fiscal year 2026 and US$0.7 billion for the fourth quarter compared with US$2.3 billion and US$1.0 billion for the same periods in fiscal 2025. Fourth-quarter revenue of US$744.1 million was down 29% year on year. Fluence said revenue in both periods was weaker than expected primarily due to shipment delays associated with the ramp-up of its contract manufacturer’s facility in Houston.
Margins took the heavier hit. GAAP gross profit margin was 2.8% for fiscal year 2026 and negative 5.0% for the fourth quarter, compared with 13.1% and 13.7% a year earlier. Fluence said margins were primarily hit by liquidated damages from project delays tied to the Houston ramp-up and by cost overruns on new product deployment. The net loss reached US$273.9 million for the year and US$137.8 million for the quarter, against a US$68.0 million loss and US$24.1 million profit in the prior-year periods. The loss per Class A share was US$1.51 for the year, against US$0.37 in fiscal 2025.
Two balance sheet lines show the delivery problem in physical terms. Inventory more than doubled to US$968.6 million from US$455.0 million a year earlier, a 113% rise, as product built up faster than it shipped. Deferred revenue rose 53% to US$978.1 million from US$640.5 million, reflecting customer payments received for work not yet delivered. Cash and cash equivalents fell 49% to US$352.8 million from US$690.8 million, and free cash flow was negative US$278.4 million for the year against negative US$160.4 million in fiscal 2025.

What an US$8.9 billion backlog means when annual revenue is US$2.3 billion
The backlog is now 3.8 times Fluence’s fiscal 2026 revenue, which means the company holds almost four years of sales on its books at the current run rate. Fourth-quarter orders alone, at US$3.5 billion, were 4.7 times fourth-quarter revenue of US$744.1 million. That ratio cuts both ways: it is the strongest forward visibility Fluence has ever reported, and it concentrates the risk on execution. The release itself warns that backlog may not convert to revenue in the expected period, or at all, and that customers can delay or cancel orders.
Bernerd Da Santos, executive vice president and chief operating officer, said: “We are focused on enabling Fluence to capitalize on our competitive strengths, including our differentiated product. Our transformation strategy is designed to deliver on our commitments to customers, improve financial and operational execution, prioritize profitable growth, and strengthen cash generation.” The company is run by a newly constituted executive team, with Meier as interim chief executive, and the transformation plan is built around fixing the manufacturing and delivery chain that produced the Houston delays.
The demand side has a structural tailwind. US battery storage passed 200 GWh of installed capacity in the third quarter of 2026, with 14.3 GWh installed in the quarter alone, as Joule Post reported in US Battery Storage Passes 200 GWh as Third-Quarter Installations Hit 14.3 GWh. Data centres are adding a new customer class on top of utility demand: Fluence’s 10% data-centre backlog share and the US$586 million hyperscaler order in the quarter show storage moving into the AI power buildout. For context on the technology, see Tesla Megapack Explained: Cost, Capacity and How Grid-Scale Battery Storage Works and the long-duration storage cost guide.
The test for Fluence in fiscal 2027 is narrow and measurable: convert the backlog into shipped systems without repeating the Houston delays, and restore gross margin from negative territory toward the double-digit levels of fiscal 2025. The orders prove customers want the product. The next four quarters will show whether the company can build it on time.