• Green Volt reserved 28 Siemens Gamesa turbines of more than 15 MW each for its 560 MW floating wind farm off Peterhead, Scotland, a world first for commercial-scale floating wind.
  • The deal reserves manufacturing capacity and engineering resources rather than placing a firm turbine order, and it covers the project’s 400 MW Contract for Difference.
  • At about £4.46 million per MW, the project’s expected £2.5 billion investment sits within 4% of the per-MW cost of the fixed-bottom Vanguard project.

The Green Volt floating wind farm’s turbine deal, announced on 24 November 2026, reserves factory slots rather than buying machines outright, and that distinction is the point. A reservation secures manufacturing capacity and specialist engineering resources for 28 Siemens Gamesa turbines, putting Green Volt at the front of a production queue contested by every offshore wind developer in Europe. The 400 MW Contract for Difference the project won in 2024 is fully covered by the reserved capacity, which is what makes the deal bankable even before a final investment decision.

Green Volt sits about 50 miles off Peterhead on Scotland’s east coast and holds consent for up to 560 MW of generating capacity. The project already holds a 400 MW Contract for Difference from the UK government, awarded in 2024, and offshore consent from the Scottish government. It is designed to feed renewable electricity into the UK grid and to help decarbonise offshore oil and gas operations, the dual purpose that has made it a flagship for Scotland’s floating wind ambitions.

Aerial view of the Block Island offshore wind farm turbines in open water
Ionna22 / Wikimedia Commons, CC BY-SA 4.0

A reservation, not an order, and why that still matters

The distinction between reserving turbines and ordering them is the honest core of this announcement. A firm order would mean contracts signed, deposits paid and delivery dates fixed. A reservation means Siemens Gamesa has set aside factory capacity and engineering teams for 28 machines, and Green Volt has secured its place in a production queue that is contested by every offshore wind developer in Europe. For a project that has not yet reached a final investment decision, that is a meaningful de-risking step, and Siemens Energy’s UK and Ireland managing director Darren Davidson described it in exactly those terms: “reserving manufacturing capacity for 28 of our 15 MW turbines is a meaningful step in moving the project forward.”

Green Volt project director Matt Green called the agreements “landmark” and “a defining moment for floating offshore wind”, adding that “reserving turbines of this scale is a world first.” The project has important milestones ahead, as Davidson acknowledged, but the reservation puts a critical part of the supply chain in place before construction rather than after it.

What £4.46 million per MW says about floating wind costs

The cost comparison is where this announcement carries its real news value. Green Volt is expected to drive around £2.5 billion (pounds sterling) of investment. Divided by 560 MW of consented capacity, that is about £4.46 million per MW. The fixed-bottom benchmark is RWE and KKR’s Vanguard project, two 1.4 GW wind farms off Norfolk that reached financial close on 11 November 2026 with about £12 billion of total investment for 2.8 GW, or about £4.29 million per MW. On those figures, floating wind’s headline cost per MW sits about 4% above a fixed-bottom mega-project, a gap far narrower than the industry’s reputation for expensive floating technology would suggest.

Project Technology Capacity Investment Cost per MW
Green Volt, Scotland Floating 560 MW About £2.5 billion About £4.46 million
Vanguard West and East, England Fixed-bottom 2,800 MW About £12 billion About £4.29 million
Hywind Tampen, Norway Floating 88 MW — —

The comparison needs its caveats stated plainly. Green Volt’s £2.5 billion is the developers’ expected investment figure, while Vanguard’s £12 billion is the total investment at financial close, so the two numbers are not compiled on identical bases. Vanguard is also five times Green Volt’s size, and scale alone cuts per-MW costs. Even with those caveats, the direction is the story: floating wind is no longer priced in a different league from fixed-bottom. The scale context reinforces it. At 560 MW, Green Volt would be more than six times the size of Hywind Tampen, the 88 MW Norwegian array that is the world’s largest floating wind farm in operation today, opened in August 2023.

The 420 MW gap inside a 560 MW consent

The reservation covers 28 turbines of more than 15 MW each, which is at least 420 MW of capacity. That neatly covers the project’s 400 MW Contract for Difference, the revenue-backed portion that makes financing possible. It leaves about 140 MW of consented capacity without reserved turbines, a gap the developers will need to close with a further order or a larger turbine rating before the full 560 MW can be built. The arithmetic is straightforward, and it sets the next milestone: a firm procurement decision covering the remaining capacity.

Construction is expected to generate more than 2,800 direct jobs, or five jobs per MW of consented capacity, and about 100 long-term roles over the wind farm’s operational life. Those figures matter in Aberdeen, where the energy transition is measured in jobs as much as megawatts, and they explain why the announcement drew statements from both the UK energy minister Michael Shanks and Scotland’s energy minister Stephen Gethins.

Aberdeen’s £15 million port investment

Alongside the turbine reservation, Green Volt signed a letter of intent with Port of Aberdeen for future anchor and mooring marshalling at Aberdeen South Harbour. The agreement is expected to support a £15 million package of investment and expenditure across port infrastructure, facilities and supply-chain activity, though the investment is subject to final confirmation. The port has already invested £420 million in South Harbour, and its chief executive Bob Sanguinetti said the deepwater berths and laydown space are “ideal for floating wind projects”.

The port deal matters because floating wind is assembled differently from fixed-bottom wind. Turbines are built and floated out from port, with anchors and mooring lines marshalled onshore, so the port is effectively part of the factory. Aberdeen’s bet is that the capability built for Green Volt will serve the wider ScotWind and INTOG pipelines, and the letter of intent is the first step toward that.

What happens next

Green Volt still has to convert a turbine reservation into a firm order, close its financing, and take a final investment decision. The 400 MW Contract for Difference gives it a contracted revenue stream, and the turbine reservation gives it a place in the manufacturing queue, but neither is construction. The project’s own language is careful on this point, and it should be read that way.

Even so, the direction of travel is clear. A floating wind farm of 560 MW, with turbines above 15 MW reserved at commercial scale, would be the largest of its kind in the world by a wide margin. If Green Volt reaches construction on schedule, it will show whether floating wind can move from demonstration arrays of tens of megawatts to commercial projects of hundreds, at a cost per MW within a few percent of fixed-bottom. That is the test the whole sector is watching.

For the technology behind the project, our guide to floating offshore wind turbines explains how the platforms work in water too deep for fixed foundations, and our guide to how wind turbines work covers the machines themselves. The fixed-bottom benchmark in this article is our report on RWE and KKR’s £12.8 billion Vanguard financing.

Sources

  • Port of Aberdeen, “World-first turbine deal and £15m Port of Aberdeen investment for Green Volt floating wind farm”, 24 November 2026. portofaberdeen.co.uk
  • Modern Power Systems, “Green Volt signs deal with Siemens Gamesa for offshore wind turbines”, 25 November 2026. modernpowersystems.com
  • Equinor, “The world’s largest floating offshore wind farm officially opened”, 23 August 2023 (Hywind Tampen, 88 MW). equinor.com