• Mexico’s installed solar capacity is forecast to rise from 13.7 GW in 2025 to 43.8 GW by 2035, more than tripling in a decade, according to GlobalData’s latest power market report.
  • The new forecast is 6 GW higher than GlobalData’s December 2025 estimate, a 16 percent upgrade in under a year, driven by a project pipeline above 45 GW led by solar.
  • The boom does not end gas: thermal plants are still expected to supply nearly 60 percent of Mexico’s electricity in 2035, and transmission losses near 12 percent plus north-to-centre congestion could slow connections.

GlobalData raised its Mexico solar capacity outlook by 6 GW in under a year, and the reason is the pipeline: more than 45 GW of power generation projects in development, dominated by solar. The consultancy’s Mexico Power Market Trends and Analysis report, published in November 2026, puts the national solar fleet on a path to more than triple over the next decade, while total installed generation reaches 156 GW.

The revision has a clear driver: the pipeline. GlobalData counts more than 45 GW of power generation projects in development, dominated by solar, and the government has moved to clear the way for them. The 2025 Electricity Sector Law and the binding 2025-2039 Electricity Sector Development Plan, known as PLADESE, guarantee the state utility CFE at least 54 percent of the electricity injected into the grid, while opening mixed-investment projects that pair CFE with private companies. In June 2026 the government announced a target of 22 GW of additional renewable capacity by 2030, and the energy ministry Sener has since selected 121 solar and wind projects totalling 18 GW.

Aerial view of the Topaz Solar Farm in California Valley
NASA Earth Observatory / Wikimedia Commons, public domain

Mexico in 2035: the forecast in numbers

Measure 2025 2035 (forecast)
Solar PV capacity 13.7 GW 43.8 GW
Total installed capacity 104.2 GW 156.0 GW
Renewables share of capacity 22.9% 42.3%
Renewables share of generation 14.5% 31.9%
Gas-fired capacity 53.4 GW 64.8 GW
Electricity consumption 328.5 TWh 423.2 TWh

Electricity consumption grows by 94.7 TWh over the decade, about 29 percent, driven by industrial nearshoring, data centre expansion and rising air conditioning demand. That demand growth is part of why the solar forecast rose: more consumption means more room for new generation of every kind. But it is also why the renewables share of generation, 31.9 percent in 2035, lags far behind the renewables share of capacity, 42.3 percent. Solar and wind generate only when the weather allows, so a megawatt of solar produces far fewer megawatt-hours a year than a megawatt of gas plant, and the gap between the two shares is the capacity factor arithmetic showing up in the national totals.

The paradox: solar triples and gas still wins

The most striking line in the forecast is the one about gas. Gas-fired capacity grows from 53.4 GW to 64.8 GW, an addition of 11.4 GW, and thermal plants still supply nearly 60 percent of Mexico’s electricity in 2035. Solar capacity triples, renewables take over two-fifths of installed capacity, and the generation mix barely moves past one-third renewable. The reason is arithmetic: gas plants run far more hours a year than solar plants, so each gas megawatt displaces more generation than each solar megawatt adds.

That makes Mexico’s transition a two-track story. On the capacity track, solar dominates the new build, and the 22 GW renewables target for 2030 plus the 18 GW of selected projects show the government intends to hit it. On the generation track, gas remains the backbone, and Mexico’s dependence on gas imports from the United States grows with it. The solar farm revenue guide explains the project economics behind the build-out, and the utility-scale cost guide covers what the new capacity costs to build.

Where the US$21.1 billion goes

GlobalData expects about US$21.1 billion of investment in new power generation capacity between 2026 and 2030. Solar takes the largest share at 44.0 percent, about US$9.3 billion, ahead of gas at 29.4 percent and wind at 20.9 percent. The solar share is the highest of any technology, which matches the pipeline: solar dominates the 45 GW of projects in development, and the six photovoltaic projects totalling 649 MW that regulator CNE approved in early November 2026, with about US$750 million of investment and commissioning scheduled for 2028 and 2029, are the first of that wave to clear permitting.

CFE’s own plans add a further layer. The state utility has raised planned investment in its mixed-capital renewable portfolio to US$10.6 billion, covering 8,026 MW of generation capacity and more than 2,500 MW of energy storage. The storage figure matters: 2,500 MW of batteries alongside new solar is the tool that turns midday solar output into evening power, and it is the part of the plan that addresses the generation-share gap described above.

Attaurrahman Ojindaram Saibasan, a power sector analyst at GlobalData, said: “Mexico is not lacking in projects or resources. The pace of the transition will depend on whether the mixed-investment model can attract international developers – following years of regulatory uncertainty – and on whether the CFE can expand transmission infrastructure quickly enough.”

The grid is the constraint

The forecast’s warning is about wires. GlobalData puts transmission and distribution losses at around 11.5 percent, and PLADESE reports combined technical and non-technical losses of 12.3 percent for 2024. Congestion on the lines connecting northern generation sites with demand centres in central Mexico and the Bajio region could slow the connection of new projects. A solar farm that cannot deliver its power earns nothing, and the pipeline’s 45 GW is worthless without the transmission to carry it.

The constraint is already visible in the approvals data. The six CNE-approved projects in early November total 649 MW with battery storage, a small share of the pipeline, and their commissioning dates of 2028 and 2029 show the lag between approval and operation. Whether the 43.8 GW figure is reached depends on the grid build-out keeping pace with the project pipeline, and on the mixed-investment model attracting the international developers Saibasan names. The power purchase agreement guide explains the contracts under which most of these projects will sell their power, and the terms of those contracts decide whether the pipeline converts into steel in the ground.